杨玉中, 王飞, 黄卓敏. 郭村煤矿12041工作面矿压数值模拟[J]. 煤矿安全, 2013, 44(9): 228-231.
    引用本文: 杨玉中, 王飞, 黄卓敏. 郭村煤矿12041工作面矿压数值模拟[J]. 煤矿安全, 2013, 44(9): 228-231.
    YANG Yu-Zhong, WANG Fei, HUANG Zhuo-min. Numerical Simulation on Rock Pressure at 12041 Working Face in Guocun Coal Mine[J]. Safety in Coal Mines, 2013, 44(9): 228-231.
    Citation: YANG Yu-Zhong, WANG Fei, HUANG Zhuo-min. Numerical Simulation on Rock Pressure at 12041 Working Face in Guocun Coal Mine[J]. Safety in Coal Mines, 2013, 44(9): 228-231.

    郭村煤矿12041工作面矿压数值模拟

    Numerical Simulation on Rock Pressure at 12041 Working Face in Guocun Coal Mine

    • 摘要: 运用有限元数值模拟软件FLAC3D,模拟在12041工作面及工作面上下平巷开挖前后,所受应力影响及位移变形。开挖巷道后,巷道顶底板在一定范围内卸压,出现拉应力区域,巷道交叉口和工作面前方10 m处出现应力集中。模拟过程中发现1个“坚硬岩层”,为第六组砂岩。

       

      Abstract: Numerical simulation software FLAC3D is used to simulate the stress, deformation and displacement of 12041 working face and up and down crossheadings before and after the excavation. After the excavation of the tunnel, the tunnel roof and floor releases pressure within a certain range, and appears tensile stress area. stress concentration appears in roadway intersections and ten meters in front of the square. The simulation process found a hard rock, the sixth sandstone.

       

    /