崔明奎. 厚煤层一次采全高工作面预掘停采机道停采技术[J]. 煤矿安全, 2012, 43(6): 44-46.
    引用本文: 崔明奎. 厚煤层一次采全高工作面预掘停采机道停采技术[J]. 煤矿安全, 2012, 43(6): 44-46.
    CUI Ming-kui. Stopping Mining Technology of Pre-excavating Stop Mining Machine Road in Mining Overall Height in One Time Working Face of Thick Seam[J]. Safety in Coal Mines, 2012, 43(6): 44-46.
    Citation: CUI Ming-kui. Stopping Mining Technology of Pre-excavating Stop Mining Machine Road in Mining Overall Height in One Time Working Face of Thick Seam[J]. Safety in Coal Mines, 2012, 43(6): 44-46.

    厚煤层一次采全高工作面预掘停采机道停采技术

    Stopping Mining Technology of Pre-excavating Stop Mining Machine Road in Mining Overall Height in One Time Working Face of Thick Seam

    • 摘要: 晋华宫矿南山区域12#煤层8212工作面为一次采全高工作面,针对设备运输尺寸大、煤层厚,停采支护困难,占用时间长的问题,通过预先掘进停采机道,缩短停采支护时间,实现了工作面安全快速停采,创造了可观的经济效益。

       

      Abstract: The 8212 working face in No.12 coal seam of Jinhuagong coal mine is mining overall height in one time working face.Aiming at the problems of large size of transport equipment,thick seam,difficulty of stop mining support,occupancy of long time,safe and fast stop mining on working face is achieved by pre-excavating stop mining machine road,shortening the time of stop mining support,which creates a considerable economic benefits.

       

    /