李明, 董蒙蒙, 王艾妩, 马熹焱. 天池能源南露天煤矿板裂结构岩体顺层边坡溃屈破坏变形演化规律及锚固参数研究[J]. 煤矿安全, 2022, 53(8): 225-229.
    引用本文: 李明, 董蒙蒙, 王艾妩, 马熹焱. 天池能源南露天煤矿板裂结构岩体顺层边坡溃屈破坏变形演化规律及锚固参数研究[J]. 煤矿安全, 2022, 53(8): 225-229.
    Research on buckling failure and anchorage parameters of slab-rent structure rock bedding slopes in Tianchi Energy South Open-pit Coal Mine[J]. Safety in Coal Mines, 2022, 53(8): 225-229.
    Citation: Research on buckling failure and anchorage parameters of slab-rent structure rock bedding slopes in Tianchi Energy South Open-pit Coal Mine[J]. Safety in Coal Mines, 2022, 53(8): 225-229.

    天池能源南露天煤矿板裂结构岩体顺层边坡溃屈破坏变形演化规律及锚固参数研究

    Research on buckling failure and anchorage parameters of slab-rent structure rock bedding slopes in Tianchi Energy South Open-pit Coal Mine

    • 摘要: 根据新疆天池能源南露天矿板裂结构岩体顺层边坡变形及溃屈破坏的特征,借助边坡雷达监测手段,通过将滑坡破坏过程预测转化为边坡岩体渐进破坏的判断,分析了边坡雷达坡表位移速率与边坡变形及溃屈破坏的内在联系,并基于弹性板理论探讨了边坡溃屈破坏长度与锚固参数的关系。研究结果表明:受张拉裂缝扩张及底滑面出露影响,板裂结构岩体破坏前的强烈弯曲-隆起阶段坡表雷达位移速率呈现明显下降趋势;坡表雷达位移速率下降至最小值的拐点可作为溃屈破坏边坡失稳的图解判据和临滑预警时间节点;锚固排距小于边坡溃屈破坏极限长度时,锚杆(索)可有效提高板裂岩体抗弯刚度,用于板裂岩体溃屈破坏治理效果显著。

       

      Abstract: In this paper, according to the characteristics of bedding slope deformation and buckling failure of slab cracked rock mass in Xinjiang Tianchi Energy South open-pit Coal Mine, with the help of slope radar monitoring means, by transforming the prediction of landslide failure process into the judgment of gradual failure of slope rock mass, the internal relationship between slope radar slope surface displacement rate and slope deformation and buckling failure is analyzed, and based on elastic plate theory, the relationship between slope buckling failure length and anchorage parameters is discussed. The results show that the radar displacement rate of slope surface shows an obvious downward trend in the strong bending uplift stage before the failure of slab cracked rock mass due to the expansion of tension cracks and the exposure of bottom sliding surface; the inflection point at which the radar displacement rate on the slope surface drops to the minimum value can be used as the graphical criterion of slope failure and the time node of critical sliding early warning; when the anchor row spacing is less than the ultimate length of slope buckling failure, the anchor bolt(cable) can effectively improve the flexural stiffness of plate cracked rock mass, and the treatment effect of plate cracked rock mass buckling failure is remarkable.

       

    /