    亭南煤矿工作面定向长钻孔“区域预抽+卸压防冲”可行性分析

    Feasibility analysis of “regional pre-pumping and pressure relief and anti-impact” of directional long borehole in Tingnan Coal Mine working face

    • 摘要: 针对亭南煤矿在402工作面回采前利用普通钻机施工卸压钻孔过程中存在钻孔施工成本高、施工周期长、钻孔偏斜造成该区域抽采钻孔漏风、抽采负压减小、同时多道工序施工之间相互干扰影响巷道掘进效率等问题,通过数值模拟,利用定向钻机采用?准120 mm的定向长钻孔抽采工作面回采区域内瓦斯,采用?准150 mm的定向长钻孔对工作面回采巷道迎头和巷帮进行大直径钻孔卸压,对比分析了定向长钻孔超前迎头500 m与卸压孔超前迎头30 m施工后,超前迎头应力峰值位置、应力集中区分布范围、应力降低区分布范围、塑性区分布范围等的分布特征。结果表明:定向长钻孔卸压后的应力峰值基本分布于距巷帮2.5 m左右,且高应力集中区主要分布在距巷帮2~5 m范围,在此范围内补打定向长钻孔卸压后,应力峰值向煤体深部转移,应力集中范围减小,卸压范围增大,具有更好的卸压效果。

       

      Abstract: In view of the common use before mining at 402 face in Tingnan Coal Mine, there are some problems in the process of pressure relief drilling, such as high drilling cost, long construction period, drilling deviation, which will cause air leakage in the extraction drilling hole in this area, reduce the negative pressure of extraction and mining, and influence the efficiency of roadway excavation by the mutual interference between the construction of multiple processes, through numerical simulation, the directional drilling machine adopts the directional long borehole of 120 mm to extract the gas in the mining area of the working face, and the directional long borehole of 150 mm is used to relieve the pressure of the roadway head and the roadway side of the working face. The distribution characteristics of stress peak position, stress concentration zone, stress reduction zone and plastic zone in the lead head of directional long drilling hole with 500 m and 30 m ahead head of pressure relief hole were compared and analyzed. The results show that the stress peak of directional long borehole after pressure relief is basically distributed about 2.5 m away from the roadway, and the high stress concentration area is mainly distributed in the range of 2-5 m away from the roadway. In this range, the stress peak is transferred to the deep part of the coal, the stress concentration range is reduced, and the pressure rerange is increased, which has a better pressure relief effect.

       

    /