巴拉素长距离掘进工作面供风量衰减规律研究

    Study on attenuation law of air supply in Balasu long-distance driving face

    • 摘要: 在长距离通风领域,风筒供风量衰减规律对于局部通风系统的风量调控与节能降耗具有重要意义。为了提升巴拉素煤矿2201长距离运输掘进巷道的局部通风效率,减少风筒漏风带来的安全隐患和能耗,针对长距离风筒的漏风问题开展研究。基于流体动力学与非线性渗流理论建立了风筒等效漏风面积计算模型,以风机风压、掘进长度、入口风量为边界条件,采用Fluent软件进行长距离风筒漏风数值模拟,开展工作面供风能力预测并给出不同掘进长度时的局部通风机供风方案。研究结果表明:基于风筒等效漏风理论的现状模拟效果较好,当掘进长度为2 000~3 000 m时,风筒单元长度设置为400 m,等效漏风口面积设置为0.003 768 m2,风筒出风量模拟误差均在0.4%以下,风压模拟误差均在5.8%以下;当局部通风机供风量一定时,风筒内风压与运移风量分别随掘进长度的增加呈线性与超线性衰减关系,风筒漏风处内外压力差与漏风量成二次函数关系,百米漏风率随风筒长度的增加呈现负指数增大趋势。基于研究结果,不同掘进长度下的风机供风量调整方案为:当掘进长度为3 000~5 000 m时,风机功率不变,保持供风量650 m3/min即可;当掘进长度为5 000~5 500 m时,需要增大风机供风量至700 m3/min;当掘进长度为5 500~6 000 m时,需要再次增大风机供风量至900 m3/min。

       

      Abstract: In the field of long-distance ventilation, the attenuation law of air supply from the wind duct is of great significance for the air volume regulation and energy saving of the local ventilation system. In order to improve the local ventilation efficiency of the 2201 long-distance transportation roadway in Balasu Coal Mine, and to reduce the safety hazards and energy consumption caused by the air leakage of the wind duct, we study the air leakage problem of the long-distance wind duct. Based on the fluid dynamics and nonlinear seepage theory, the equivalent air leakage area calculation model of wind duct was established, and Fluent software was used to carry out the numerical simulation of wind leakage of long-distance wind duct with the boundary conditions of wind pressure of fan, tunneling length and inlet air volume, to carry out the prediction of the air supply capacity of the working face, and to give the local ventilator air supply scheme for different tunneling length conditions. The study shows that: the current simulation effect based on the theory of equivalent air leakage of the wind duct is better, when the advancing length is 2 000-3 000 m, the length of the wind duct unit is set to 400 m, and the area of equivalent air leakage port is set to 0.003 768 m2, the simulation error of wind duct air volume is below 0.4%, and the simulation error of wind pressure is below 5.8%; when the local fan air supply is certain, the wind pressure and the transported air volume are respectively increased with the advancing length and inlet air volume, and the wind pressure and the transported air volume are decreased with the advancing length, and the local fan air supply scheme is given. When the air supply of local ventilation fan is certain, the air pressure and air volume of air transport in the wind pipe show linear and super-linear attenuation respectively with the increase of advancing length, the pressure difference between the inside and outside of the wind pipe leakage and air leakage becomes a quadratic function relationship, and the air leakage rate of 100 metres shows a negative exponential trend with the increase of the length of the wind duct. Based on the study results, the adjustment scheme of fan air supply under different advancing length conditions is proposed, when the advancing length is 3 000-5 000 m, the fan power remains unchanged, and the air supply can be maintained at 650 m3/min; when the advancing length is 5 000-5 500 m, the fan air supply needs to be increased to 700 m3/min; when the advancing length is 5 500-6 000 m, the fan air supply needs to be increased again to 900 m3/min.

       

    /

    返回文章
    返回