曹家滩矿综采工作面覆岩运移及垮落带可充填空间研究

    Study on overlying strata movement and fillable space of caving zone in fully mechanized mining face of Caojiatan Coal Mine

    • 摘要: 在煤层开采过程中,如何实现规模化处置煤矸石一直是煤炭行业绿色、高效发展亟待解决的重要难题。垮落带采动空隙作为矸石注浆充填的主要空间,其演化过程与覆岩运移密切相关。通过分析垮落带覆岩运移规律,发现垮落带可充填空间是解决上述问题的根本途径之一。以曹家滩煤矿122109超大采高工作面为研究对象,采用相似模拟试验和理论分析相结合的方法,研究了采空区垮落带的形态特征、覆岩下沉规律及垮落带可充填空间,揭示了覆岩运移自下而上逐渐发展的演化规律。在此基础上,利用ImageJ软件处理图片,计算得到裂隙网络图的分形维数,定量表征了裂隙的发育程度与复杂性。结果表明:工作面开采条件下,垮落带覆岩裂隙发展可分为裂隙发育阶段、裂隙加速发育阶段、压实阶段、裂隙整体平稳阶段等变化阶段;垮落带空隙面积占比为28.6%,其空隙空间“O形圈”靠运输巷侧空隙、裂隙带和垮落带间的离层区、“O形圈”靠回风巷侧空隙及垮落带内部空隙占比分别为14.6%、14.0%、15.1%、56.3%;基于垮落带松散岩石的空隙计算模型,得到垮落带内松散岩石空隙率为29.13%,垮落带可充填空间536.6 万m3,垮落带单侧矸石可充填量为206.5 万t,充填率为9.4%。

       

      Abstract: In the process of coal seam mining, how to achieve large-scale disposal of coal gangue has always been an important problem to be solved in the green and efficient development of the coal industry. As the main space for gangue grouting and filling, the evolution process of mining voids in the caving zone is closely related to the movement of overburden rock. By analyzing the movement law of overlying strata in the caving zone, it is found that the fillable space of the caving zone is one of the fundamental ways to solve the above problems. Taking the 122109 ultra-large height working face of Caojiatan Coal Mine as the research object, a method combining similarity simulation experiment and theoretical analysis was adopted to study the morphological characteristics of the caving zone, the subsidence law of the overlying strata, and the fillable space of the caving zone. The evolution law of the overlying strata moving from bottom to top gradually was revealed. Based on this, the images were processed using the ImageJ software, and the fractal dimension of the fracture network diagram was calculated. This quantitatively characterized the development degree and complexity of the fractures. The results show that under the working face mining conditions, the development of overlying rock fractures in the caving zone can be divided into stages such as the stage of fracture development, the stage of accelerated fracture development, the stage of compaction, and the stage of overall stable fracture; the proportion of void area in the caving zone is 28.6%, and the void space on the side of the transportation roadway of the “O-shape ring”, the bed separation zone between the caving zone and the fractured zone, and the void space on the side of the return air roadway of the “O-shape ring” and the void space within the caving zone account for 14.6%, 14.0%, 15.1%, and 56.3% respectively. Based on the void calculation model of the loose rocks in the caving zone, the void ratio of loose rocks in the caving zone is 29.13%, the available filling space of the caving zone is 5 366 000 m3, the available filling volume of the coal gangue on one side of the caving zone is 2 065 000 t, and the filling rate is 9.4%.

       

    /

    返回文章
    返回